An approval due on launch day is usually too late for a campaign with localisation, captioning and partner delivery. A workable review schedule begins with the moment the final approved asset must leave the studio and identifies each decision that has to happen first.
Work backwards with named reviewers
Suppose the distributor needs the final video on Thursday morning. Allow time for localised exports, check the export against the approved cut, reserve an edit window and ask the client to approve the master before those tasks begin. Name one person who can consolidate conflicting feedback. Give each reviewer the version, decision requested and deadline in their own time zone.
Make a missed decision visible
If feedback arrives after the export window, identify which tasks can still proceed and which release entries now need new dates. Present the producer with the impact and available choices before changing the schedule. The cleared asset and publication schedule in Numerish give campaign teams a common reference for recording the revised decision.
More to discover in Numerish.
Explore related insights and practical enterprise workflows.