A consulting team has committed to a three-week diagnostic. Interviews are booked, but analysis depends on an extract only the client’s data owner can release. Listing “data availability” as a general risk gives the engagement manager little guidance about when to intervene.
Give each dependency a usable definition
Record the exact file or decision, expected format, responsible client contact, required date and the activity it enables. If a dummy extract will let the team prepare a model, agree when it can arrive and which checks still require real data. Keep assumptions about completeness visible.
Decide what happens if the date moves
Suppose the extract will arrive four days late. The team could bring forward interviews, resequence the analysis or seek a revised review date. Identify which option protects the client’s priority outcome and who may approve it. In the following status update, show the changed forecast and the outstanding client action together so the sponsor can make a decision.
More to discover in Numerish.
Explore related insights and practical enterprise workflows.