Construction RFIs: How to Write a Question the Designer Can Close

Turn a site question into an answer the team can apply by identifying the affected location, drawing and decision before sending an RFI.

Two people point to details on a printed building plan at the jobsite.
Construction / Numerish Insight
Jump to a section
  1. 01Put the conflict in one place
  2. 02Close the loop with the recipient

A pipe sleeve appears in two positions on the same floor. Asking the designer to “confirm the layout” can produce a technically correct reply that leaves the installer guessing. A useful request for information identifies the single decision blocking a named activity. The site engineer owns the question until somebody has accepted responsibility for answering it.

Put the conflict in one place

Record the two drawing references and their revisions, the grid intersection and the conflicting dimensions. Attach a marked extract showing both positions. State when the sleeve layout must be released to the installation team and why. If identical details occur on three floors, ask whether the answer applies to all three. An unanswered question about scope can turn one clarification into three site visits.

Close the loop with the recipient

Suppose the designer confirms position B on level two only. Send the answer and location to the supervisor, then record the separate decision still needed for levels three and four. At the coordination meeting, review RFIs whose answers have arrived but have yet to reach the people setting out the work.

Explore the Numerish construction workflows.

KEEP EXPLORING

More to discover in Numerish.

Explore related insights and practical enterprise workflows.

Browse all insights
FROM INSIGHT TO ACTION

Put the ideas to work.

Discover enterprise workflows for construction teams.

Explore Construction