A site team receives a revised drawing that moves a plant room wall. The crew needs an answer before tomorrow’s pour. The drawing explains what to build, but it does not establish who will pay for the additional work. A contractor needs an answer to both questions while there is still time to act.
The Numerish construction workflow separates the request for information, the assessment of time and cost, and the authorised variation. That separation gives the site manager a current technical instruction and the commercial manager a traceable basis for valuing the work.
Identify exactly what changed
Record the location, the previous drawing revision and the replacement. Describe the difference in language the site engineer and quantity surveyor can both verify. An instruction to “revise the wall” leaves room for disagreement. A marked-up revision and a measured change in length give the estimator something to price.
Use the project record to connect the design issue in AEC360 to the commercial assessment and contract authority. Record who may issue the instruction and what needs to happen if work is urgent. Contract terms and delegated authority determine that choice for each project. Follow the design-change workflow.
Read the variation against forecast margin
Consider a package with an agreed value of 500,000 and forecast cost of 450,000. Its forecast margin is 50,000. If a change adds 18,000 of expected cost, the forecast margin falls to 32,000 while the contract value stays the same. If an additional 22,000 is subsequently approved, the revised forecast becomes 54,000. All figures are illustrative and exclude tax.
Keeping those positions separate matters. The project director needs to see the cost exposure while the variation is pending. The person preparing a payment application needs the approved value and the evidence required for certification. A pending quotation cannot serve both purposes.
Bring the right exceptions to the weekly review
For open changes, review the age of the instruction, estimated exposure, named decision owner and next contractual date. For approved changes, check whether the valuation schedule and current drawing issue agree. Compare incorporated variations with amounts submitted and certified.
As the contractor takes on more projects, this gives management a consistent question to ask on every site. Which committed costs are still waiting for commercial authority? Explore how Contract360 tracks obligations.