A fixed-fee engagement has used 60 of its planned 100 hours. The team reports that it is “about halfway through.” That judgement is a useful signal, but the manager needs a forecast tied to actual work. Ask the people doing the remaining work for an estimate by deliverable.
Forecast from what is still open
Suppose analysis needs 12 hours, drafting needs 22 and client review support needs 10. Adding those 44 hours to the 60 already used gives an expected total of 104. Include time for corrections and handover if those activities were part of the original commitment. Flag assumptions still awaiting a client decision.
Make the forecast change a decision
A four-hour overrun could reflect extra work, an underestimated task or temporary duplication. Inspect the cause before changing staffing or asking for a scope decision. Save the approved baseline beside the latest forecast so a partner can see both what the practice promised and what the team currently expects to spend.
More to discover in Numerish.
Explore related insights and practical enterprise workflows.