A component costs 14 each for an order of 80 or 11 each for 200. Purchasing may celebrate the discount while stores inherits inventory that no one has committed to use. Put the buyer and demand owner in front of the same quantity decision.
Separate immediate demand from later use
The smaller order requires 1,120. The larger one requires 2,200 and leaves 120 units once today’s demand is covered. Ask when the next 120 are expected to be consumed, where they fit and whether a design change could make them unusable. Record which demand is firm and who owns the forecast.
Negotiate the constraint
The supplier may need a production run of 200 but accept staged releases. Ask who holds the balance, which dates are binding and how freight changes. Compare this with a smaller order at the higher price. Preserve the approved quantity and delivery arrangement in the order so inventory and finance can plan for the same commitment.