Materials on Site: How to Separate Delivery from Installed Progress

Use three distinct records to distinguish delivered, eligible and installed materials when preparing a construction valuation.

Stacks of red clay bricks sit ready for use on a construction site.
Construction / Numerish Insight
Jump to a section
  1. 01Track each change in status
  2. 02Carry the balance forward

A site store receives forty doors just before the valuation date. Ten are hung. A delivery note proves that the shipment arrived, while the subcontract terms determine how much work or material may be valued. Treating all forty as installed distorts progress and makes a later application harder to reconcile.

Track each change in status

Give the delivery a batch or location reference. Record the quantity received, units rejected on arrival, units held in storage and units installed and accepted. Ask the commercial reviewer to identify the applicable valuation basis for stored materials. Save the delivery and inspection references with the application so the next reviewer can reproduce the decision.

Carry the balance forward

Suppose thirty doors remain in storage and the reviewer accepts a separate allowance for that stock. In the next period, eight are installed. Transfer eight from the stored balance into the relevant work item and account for the earlier allowance in the calculation. A stock balance of twenty-two gives site and commercial teams a simple cross-check before certification.

Explore the Numerish construction workflows.

KEEP EXPLORING

More to discover in Numerish.

Explore related insights and practical enterprise workflows.

Browse all insights
FROM INSIGHT TO ACTION

Put the ideas to work.

Discover enterprise workflows for construction teams.

Explore Construction