A production planner allows ten days for a supplier that usually ships in a week. Stock still arrives too late. The supplier’s clock starts after order acceptance. The planner’s clock starts when the business identifies the need and ends when material can be used.
Mark the events that change ownership
For one recent line, write down when the request was ready, approved, issued, acknowledged, received and released by inspection. A request opened Monday might wait two working days for clarification and another day for approval. Those three days consume the planner’s allowance before the supplier starts work.
Use the delay that can be influenced
If clarification dominates repeated cases, update the request form or provide an example for that item family. If inspection queues dominate, give receiving earlier notice of the delivery. Rerun the same exercise after the change and keep working days and calendar days consistent. This creates a grounded lead-time estimate for the next planning cycle.
More to discover in Numerish.
Explore related insights and practical enterprise workflows.