Submittal Registers: Working Back from the Installation Date

Set construction submittal priorities from installation dependencies, supplier lead times and the remaining review window.

A designer points to one of several finish samples arranged on a board.
Construction / Numerish Insight
Jump to a section
  1. 01Build the decision window
  2. 02Distinguish clarification from release

A submittal that has sat in review for a week may deserve attention before one that has waited a month. Its priority depends on what happens after review. The package manager can make that decision visible by working backwards from the date the approved item must reach site.

Build the decision window

For a six-week fabrication order due on site in week eighteen, factory release is needed by week twelve. Allow time for the supplier to incorporate comments, return documents and confirm the release. If the last practical client decision falls in week ten, show that date beside the original submission and the person currently holding it.

Distinguish clarification from release

Imagine the reviewer agrees the dimensions but asks for a revised finish sample. Ask the supplier whether fabrication can proceed in part and get the appropriate decision recorded against the package. Give procurement the exact released scope and outstanding finish decision. At the next meeting, review the remaining decision window alongside the review status. This tells the planner which downstream date needs attention first.

Explore the Numerish construction workflows.

KEEP EXPLORING

More to discover in Numerish.

Explore related insights and practical enterprise workflows.

Browse all insights
FROM INSIGHT TO ACTION

Put the ideas to work.

Discover enterprise workflows for construction teams.

Explore Construction