A supplier reports 98 percent on-time dispatch while your warehouse reports frequent late deliveries. Both could be measuring accurately. Dispatch from the supplier and availability at your site are different events. Choose the one that answers the purchasing team’s question and retain the dates needed to reconstruct it.
Define the denominator first
For an internal scorecard, consider order lines due in the period. If ten lines were due and eight arrived in full by the agreed receiving date, the on-time-in-full result is eight out of ten. State how weekends, early deliveries and buyer-requested rescheduling are handled. Apply the same rule across the sample.
Investigate the two misses
Keep the original requirement, supplier confirmation, subsequent revisions and physical receipt date. One late line might reflect a buyer change, while another missed an unchanged commitment. Discuss these causes separately at review. A scorecard has earned its place when the next meeting can assign a specific improvement and check its effect against the same definition.
More to discover in Numerish.
Explore related insights and practical enterprise workflows.