A general note reading “extra works, two operatives” is hard to price three weeks later. The site foreman and the commercial reviewer need different things from a daywork record. One confirms what happened on site. The other checks the instruction, entitlement and valuation basis against the applicable agreement.
Make the daily record specific
Identify the work area, instruction reference, activity, operatives or labour classes, hours and plant usage. Record breaks or standby separately where relevant. Attach a marked drawing or photograph when location would otherwise be ambiguous. Ask the site representative to state what their acknowledgement covers so the commercial reviewer can distinguish observed attendance from priced approval.
Give the surveyor a bounded question
For example, a crew spent six hours repositioning door frames on level four and two hours waiting for access elsewhere. Split the entries and link each to its own explanation. The surveyor can review rates and instructions against each entry. If the two waiting hours need clarification, the six hours of identified work can still be assessed on their own evidence.
More to discover in Numerish.
Explore related insights and practical enterprise workflows.