Construction Progress Valuations: Agreeing Quantities at Cutoff

Help site surveyors and commercial teams resolve measurement differences before they enter a subcontract payment certificate.

A survey total station stands on its tripod against a backdrop of trees.
Construction / Numerish Insight
Jump to a section
  1. 01Start with the last agreed position
  2. 02Issue a reproducible calculation

A subcontractor measures a continuous run of installed partitioning. The project surveyor measures by room and excludes unfinished openings. Both submit defensible totals. Without a common boundary, the commercial manager cannot explain what the current valuation actually covers or which quantities can enter the next period.

Start with the last agreed position

List each location, measurement unit and previously certified quantity. During the joint walk, mark what is complete at the agreed cutoff and use the same drawing revision for both sets of measures. Photograph or annotate disputed stretches. Keep quantities still under discussion visible even if the parties can agree the remainder of the floor.

Issue a reproducible calculation

Suppose cumulative measured work is 240 metres, the parties accept 225 and 180 were certified last month. The current agreed increment is 45 metres. Record the remaining 15 against the disputed locations, along with the person who will remeasure them. The commercial manager can now explain the current certificate, and next month’s survey starts with a reliable opening position.

Explore the Numerish construction workflows.

KEEP EXPLORING

More to discover in Numerish.

Explore related insights and practical enterprise workflows.

Browse all insights
FROM INSIGHT TO ACTION

Put the ideas to work.

Discover enterprise workflows for construction teams.

Explore Construction