A shoot may look comfortably under budget while crew invoices are still in transit. The producer needs an estimate of what it will cost to finish the approved work. That estimate should distinguish money already spent, outstanding commitments and work that still needs to be commissioned.
Calculate a forecast without counting the same work twice
Suppose a production has spent 18,000, owes another 7,000 on confirmed bookings and expects 3,000 of additional editing. Its forecast is 28,000. If an unpaid invoice is already included in actual spend, remove it from open commitments before adding the figures. Record the currency and the date of the estimate.
Choose which decision is still available
Against a budget of 26,000, the producer needs a decision on the projected 2,000 overrun. Check whether the additional edit is agreed scope, whether another cost can change, or whether the client needs to approve an increase. Keep the resulting decision with the production budget and delivery obligations in the Numerish artist workflow so the next forecast starts from the approved position.
More to discover in Numerish.
Explore related insights and practical enterprise workflows.