At project close, a single retention total gives finance little help in deciding what is payable. Two packages with equal balances can have different release dates, incomplete evidence or an earlier partial release. The commercial manager needs a schedule that explains each balance from its source documents.
Trace the amount and the trigger
For every package, record the contract reference, retention actually withheld on each certificate, releases already certified and the outstanding amount. Take release conditions from that particular agreement. Keep the date a release can be considered separate from the date someone approves it and the date finance pays it.
Use one balance to test the handoff
Suppose 12,000 has been withheld and 6,000 released. When the subcontractor requests the balance, the package owner checks the agreed evidence and identifies an outstanding handover document. Finance can see the 6,000 outstanding, who is checking the release and which document remains. When approved, reconcile the release certificate to the payment so it cannot be requested a second time.
More to discover in Numerish.
Explore related insights and practical enterprise workflows.