How to Build a Construction Retention Register by Package

Track amounts held, release conditions and supporting evidence separately for each construction package.

Scaffolding wraps a partly finished two-storey house under a blue sky.
Construction / Numerish Insight
Jump to a section
  1. 01Trace the amount and the trigger
  2. 02Use one balance to test the handoff

At project close, a single retention total gives finance little help in deciding what is payable. Two packages with equal balances can have different release dates, incomplete evidence or an earlier partial release. The commercial manager needs a schedule that explains each balance from its source documents.

Trace the amount and the trigger

For every package, record the contract reference, retention actually withheld on each certificate, releases already certified and the outstanding amount. Take release conditions from that particular agreement. Keep the date a release can be considered separate from the date someone approves it and the date finance pays it.

Use one balance to test the handoff

Suppose 12,000 has been withheld and 6,000 released. When the subcontractor requests the balance, the package owner checks the agreed evidence and identifies an outstanding handover document. Finance can see the 6,000 outstanding, who is checking the release and which document remains. When approved, reconcile the release certificate to the payment so it cannot be requested a second time.

Explore the Numerish construction workflows.

KEEP EXPLORING

More to discover in Numerish.

Explore related insights and practical enterprise workflows.

Browse all insights
FROM INSIGHT TO ACTION

Put the ideas to work.

Discover enterprise workflows for construction teams.

Explore Construction