A subcontractor asks why a bank receipt differs from the gross value on its progress certificate. The response should show the route from cumulative work to this payment. When the project accountant starts with the bank amount and works backwards from memory, previous certificates and partial payments are easy to overlook.
Build a short reconciliation
Start with the certified cumulative amount and subtract the cumulative value already certified. Identify any agreed adjustments applicable to this payment and tie each one to the certificate or account detail. Match the resulting payable to the supplier invoice, payment reference and contract package. Keep the payment date separate from the valuation cutoff.
Explain an actual difference
Suppose cumulative certified work totals 95,000 and 70,000 was previously certified. This period contributes 25,000 before adjustments. If approved payment instructions release 20,000 this week, the accountant should be able to identify where the other 5,000 stands and when its status will next be reviewed. Give the subcontractor the certificate and payment references so both ledgers can follow the same balance.
More to discover in Numerish.
Explore related insights and practical enterprise workflows.