A lift supplier offers a manufacturing slot expiring on Friday. The design team has approved the car finishes, but the latest shaft dimensions remain under review. Before a buyer commits the package, the project needs to know which decisions actually control fabrication and what the supplier would be entitled to build.
Separate the outstanding decisions
List the dimensions, interfaces and selections the supplier needs at order and those that can follow. Ask the supplier to confirm those boundaries in writing. Verify who can authorise the expenditure, what scope the proposed order covers and when the site can receive the delivery. Put the slot expiry beside these dependencies so the decision has a clear deadline.
Record what the buyer can release
If preliminary drawings can proceed while fabrication awaits final shaft information, specify that limit in the purchasing instruction. Give the design manager an owner and due date for confirmation, and tell the planner which milestone remains conditional. This preserves the value of early supplier involvement while keeping the site programme honest about the unresolved dimension.
More to discover in Numerish.
Explore related insights and practical enterprise workflows.