A planner compares two batches of the same part and concludes that the smaller batch ran slowly. The machine cycle may have been identical on both orders. Setup time can change average minutes per unit without changing production speed at all.
Separate the fixed time from the cycle
Suppose each run requires 40 minutes of setup and two machine minutes per good unit. A batch of 20 uses 80 minutes, or four per unit. A batch of 80 uses 200 minutes, or 2.5 per unit. Both have the same two-minute running cycle. Record setup and operation time separately on the routing so a reviewer can reproduce the comparison.
Make the batch decision in context
The larger run uses fewer minutes per unit but ties up the work centre longer and may create stock before demand is due. Compare the saved setup minutes with the next order waiting for the machine. A Manufacturing360 operation log gives the planner the actual time and yield needed to check whether the next batch decision still makes sense.
More to discover in Numerish.
Explore related insights and practical enterprise workflows.