A two-hour maintenance slot appears to fit between jobs on the machine calendar. The maintenance planner also needs to know when the first job actually releases the asset and when the site can accept it back into production.
Calculate the usable gap
Suppose production expects to finish at 13:10 and the next committed job needs the machine at 15:30. That gives 140 minutes. Planned service uses 110 and the scheduled handback checks need another 20, leaving ten minutes of margin. If the first order slips by 25 minutes, the planned window no longer fits. Confirm that the designated spare is available before taking the slot.
Record the scheduling choice
The planner and production supervisor can release another slot or revise the next job's commitment. Capture which order is affected and who must confirm the new start. Numerish's maintenance-request-to-restart workflow links the asset, work order, spares and production handback. This gives the next shift an explicit decision to follow if the earlier job overruns.
More to discover in Numerish.
Explore related insights and practical enterprise workflows.