Six crew members spend eight paid hours on a harvest shift. Dividing all 48 person-hours by the day's picked weight gives a figure for the whole shift. It also hides what the crew spent the afternoon doing.
Rebuild the crew movement
Suppose all six people picked in Orchard A for five hours. Four then picked in B for three hours while two sorted bins for those same three hours. The allocation is 30 person-hours for A, 12 for B and six for sorting. Ask the supervisor to confirm the move time and bin activity before posting. Entering three hours against each field would confuse clock time with person-hours.
Choose the denominator that fits the question
Use 42 picking hours to examine picking productivity for this example. Use all 48 hours when asking about the cost of that entire crew shift. In Farm360, dating the field activity and naming its crew or supervisor makes it possible to revisit the decision when production reports and payroll totals appear to disagree.