Machining reports 120 pieces complete and assembly reports only 95 received. Both supervisors can be correct. A handling unit might still be waiting in transit, or the two reports might cover different cutoff times.
Trace the job across the handoff
Take an order where machining released 120 at 14:00. Assembly booked 95 at 14:15 and a labelled tote of 25 is still at the transfer point. Record the tote against that order and destination. The receiving supervisor can confirm its arrival in the next period. Treating the 25 as finished goods or scrapping them to balance the reports would both obscure their actual location.
Agree where responsibility changes
Put the order, routing step, quantity, time and accepting work centre on the transfer reference. When receipt is partial, carry forward the remaining quantity explicitly. Use the Manufacturing360 routing log to identify the two operations involved. The planner can then distinguish an actual inventory discrepancy from a queue that may be worth addressing in the next schedule.
More to discover in Numerish.
Explore related insights and practical enterprise workflows.