Two orders fit the weekly labour budget but compete for the same press on Tuesday. Adding more people to the overall shift will not create more press minutes. The planner needs a schedule measured in the capacity of the constrained operation.
Reserve time for the full operation
A four-hour window provides 240 press minutes. Order A needs a 30-minute setup and 120 minutes of running. Order B needs a 25-minute setup and 90 minutes of running. Together they require 265 minutes. Both orders cannot finish in that window as currently planned, even though their combined running time is only 210 minutes.
Choose the sequence with consequences visible
If B has a fixed outbound collection, moving A or releasing part of A may be more sensible than putting the oldest order first. Check whether a partial run introduces another setup and confirm the revised quantity with stores. Manufacturing360's routing and work-order records give the planner named operations to reschedule and a way to compare the estimate with actual time after the shift.
More to discover in Numerish.
Explore related insights and practical enterprise workflows.